about us

Aarudhra Wind has a dedicated Installation Manager who works alongside the Project Manager both in the preparation as well as the on-site delivery of the installation. It is critical that everything has been planned, things turn up in the order (and time) required and we have the right resource on site throughout the job.

For a typical installation, the following must be completed well in advance of anything happening on site:



Site drawings including GAs, cable routes, lay-down areas, off-loading plan, etc…
Transport plan both with the turbine manufacturer and local authority (if requested)    
Single Line Diagrams and other electrical design drawings
Calculating required cable specifications and other electrical component parts (such as DBs)
Risk Assessments / Method Statements / Safe Working Procedures for all tasks
Lifting plans/lifting drawings
Ordering long-lead items such as GRPs, transformers, switchgear etc…

Once the ground works have gone in, we normally have to wait 4 weeks for the concrete to hit full design strength before starting the mechanical installation. Between the ground works and installation of the turbine, we are often back on site laying cables, constructing the sub-station and making a start on the electrics in preparation for the turbine arriving. Aarudhra Wind then typically project manages the wind turbine installation from the moment the turbine arrives on site through to its successful commissioning in line with the manufacturers requirements with the following site works taking place:



Escorting delivery wagons onto site
Safe unloading of the turbine    
Assembly of the tower, nacelle and blades
Mechanical installation using a suitable crane(s)
Electrical installation, system testing and electrical sign-off
Commissioning and fine tuning to ensure optimization
Handover of turbine to client