Aarudhra Wind has a dedicated Installation Manager who works alongside the Project Manager both in the preparation as well as the on-site delivery of the installation. It is critical that everything has been planned, things turn up in the order (and time) required and we have the right resource on site throughout the job.
For a typical installation, the following must be completed well in advance of anything happening on site:
Once the ground works have gone in, we normally have to wait 4 weeks for the concrete to hit full design strength before starting the mechanical installation. Between the ground works and installation of the turbine, we are often back on site laying cables, constructing the sub-station and making a start on the electrics in preparation for the turbine arriving. Aarudhra Wind then typically project manages the wind turbine installation from the moment the turbine arrives on site through to its successful commissioning in line with the manufacturers requirements with the following site works taking place: